[ultimate_heading main_heading=”Zurich Airport / 5th Expansion Tunnel” heading_tag=”h2″ alignment=”left” spacer=”no_spacer” spacer_position=”top” spacer_img_width=”48″ line_style=”solid” line_height=”1″ line_color=”#333333″ icon_type=”selector” icon_size=”32″ icon_style=”none” icon_color_border=”#333333″ icon_border_size=”1″ icon_border_radius=”500″ icon_border_spacing=”50″ img_width=”48″ line_icon_fixer=”10″]

1998 – 2004, Zurich Airport (Switzerland)

[/ultimate_heading]
Project
Electric and mechanical installations
Tunnel and ramp lighting
Ventilation
Signs and traffic lights
Safety and rescue equipement
CCTV, Wireless Lan, broadcast, GSM
Control and monitoring

Mandate
Project and site surveillance for electrical equipment and visual ground aids. Coordination with civil engineering, safety and rescue services

Clients
Amberg Engineering
Bächtold & Moor
Eichenberger AG
Höltschi & Schurter

Cost
CHF 5 million

Challenges
Construction in a short time-slot
First roundabout in a tunnel in Switzerland